We were out on Sunday and spent almost the entire day there.  Well my husband was definitely out there 12+ hours but myself and the kiddos were only there for about 8.  The guys worked on getting all the under foundation plumbing.  The day ended with a satisfying and healthy dinner of ice cream.




On Tuesday, the inspector came out and passed our plumbing. 

On Wednesday, Steve put down all the coil tubing for the heated floors and that inspection is scheduled for today, Thursday.

Friday he plans to pour concrete and we will have a slab to begin building.  He's spoken to our contractor and he's ready to come beginning of next week. 

The shop is almost complete and probably will be done by Friday.  Craziness! I think we figured it out to be about 6 days total for them to put together that shop.  There's much more done than what I have pictured but I haven't been able to stop out this week much.  The second photo is the color of our steel roof for both the shop and the house



Well was started on Tuesday, finished on Wednesday! Its about 400 foot deep and approximately 8 gals/minute flow.  And we came in on budget! A big hooray